Pressac
Systems, Bishopbriggs (£4.6m) [
top ]

|
|
This project comprised of 10,000m2 of accommodation
1,000m2 was office. The structure comprises large
span portal frames on mass concrete foundation.
Of particular note was the ground conditions
and drainage infrastructure on site. Firstly, the ground was
contaminated due to an old cement works with trapped layers
of topsoil at 2m depth and concrete washings causing leachate
and perched water table problems.
The site also had a fall of 3m across its width.
The result was significant earthworks to eradicate contamination
by removal and encapsulation. The drainage from the site had
to be dealt with separately, with the foul being pumped some
2km away. The surface water connected to a controlled watercourse
and an attenuation ditch was provided to ensure post development
flows matched pre-development flows. |
|
Oceaneering
Multiflex, Rosyth (£4.2m) [ top ]

|
|
This project comprised of 20,000m2 of accommodation,
1,500m2 being offices. The building is 16m high and
utilises large span portal with a central spine girder on piled
foundations. Large plant foundations and pits were accommodated
both within the building and externally which were independently
piled.
The site is heavily contaminated with significant
amounts of landfill gases. As a result, encapsulation and vented
gas membrane below the building was provided. To prevent leachate
to the River Forth, a bentonite slurry wall was provided to
the perimeter of the site. |
|
| P
C Morris – Fish Processing Factory (£1.0m) [
top ]

|
|
This project comprised 200m2 of chilled
production area and associated offices. The structure comprises
steel portal frames supported on vibrocompacted foundations
and incorporates a fully glazed feature entrance staircase.
|
|
| Nexfor,
Cowie – MDF3 Expansion (£53m) [ top
]

|
|
This project delivered a new MDF production line, and involved
the construction of 60,000m2 of manufacturing building,
as well as numerous alterations to other buildings on the plant
and associated civils work.
A particular feature was the anchorage of a 60m
high tower and formation of large press pit to exacting tolerances.
The project involved a multi national team of
designers that included Canadian, Swedish, German and British
Engineers. |
|
Almond
Engineering, Livingston (£1.2m) [ top ]

|
|
This project delivered 30,000m2 of accommodation,
8,000m2 of which was office. The structure utilises
a steel frame on pad foundation with concrete ground bearing
slab. A detailed study of both shale and coal mining records
was carried out, with significant proving surveys on site to
establish the possible presence of below-ground workings. This
resulted in the final location of the building being positioned
outwith the zone of likely influence. |
|
Production
Facility for Eness Lighting Systems, Kirkcaldy (£1.2M)
[ top ]

|
|
This project involved the development of a purpose-built unit
for the client. The structure utilises portal frames on pad
foundation. Particular successes included developing the design
around major sewers, and the application of a robust SUDS solution
on a steeply sloping site.
|
|
.