|
|
 |
 

Kings
Road Primary School, Rosyth (£4.9m)
Lauder
College, Business Learning Centre (£2.2M)
Highland
Schools PPP (1) (£16.5M)
Glasgow
University Equine Centre (£;1.5m)
Kings
Road Primary School, Rosyth (£4.9m) [
top ]

|
| This project, which
provides a replacement school, is designed to suit the changing
needs of primary education, and as such the layout is highly
flexible. As a result, the selected structure utilises a steel
frame providing a very contemporary building with complex geometry.
A particular feature was the requirement to restrict
surface water discharge to 4l/s/ha post development. This entails
design of 100m3 of hydrostorage and installation
of a hydrobrake to attenuate storm flow and restrict outflow.
|
|
Lauder
College, Business Learning Centre (£2.2M) [
top ]

|
This project provided
state-of-the-art, fully networked multi-media facilities.
The design involved the retention of an existing
3 storey block and the provision of a two storey extension to
the north and south end, while also providing a seamless connection
with the existing conference facilities.
The project was highly complex in both its geometric
form and the servicing aspect. The design utilised a braced
steel frame solution with composite insitu concrete flooring.
Update August 2004 - SBA have
just been appointed to provide a further major expansion of
the facility.
|
|
|
| Highland
Schools PPP (1) (£16.5M) [ top ]

|
| This project involved
the provision of two new secondary schools at Strontian and
Drumnadrochit, and two new primary schools at Tomatin and Spean
Bridge.
Both the secondary and primary schools utilised
similar design features, however the civil works and foundation
works were bespoke to each site. Ground conditions in the west
were very poor, with excessive depths of peat (up to 2.2m) which
necessitated bulk excavation and backfill with a raft foundation.
In Strontian, as well as peat, hard granite rockhead was encountered
which had to be broken out.
At the south end of the site, rockhead shelved
away steeply and an insitu pier with precast ground beams were
used. In the east sites, foundations utilised standard strip
foundations. The superstructure utilised primarily load-bearing
masonry, with timber trussed roof. However, in the secondary
schools, steel frame was utilised in the halls and library area. |
|
| Glasgow
University Equine Centre (£1.5m) [ top
]

|
This project comprised the provision
of 2000m2 of accommodation for veterinary care and
an exercise hall. Three main buildings made up the development
and comprised a mixture of steel portal and fully braced steel
framed structures. Due to the high visibility of the steelwork,
rolled hollow sections were used for main columns, roof and
external canopies.
Architectural stonework features, mezzanine floors
and a robust internal construction were all features of this
development. Extensive cut and fill earthworks operations were
required to platform the site, and raft foundations were utilised
and built directly off the made-up ground to support the smaller
buildings. The large hall and veterinary laboratories were supported
on deep pad footings. |
|
|