Balmossie
Estate, Broughty Ferry, Dundee (£1.3M) [
top ]

|
|
As part of the housing development the site infrastructure necessitated
the crossing of an existing watercourse. The design adopted
utilised the design and construction of a new bridge to access
the site. The bridge is 16m span and is constructed using in
situ concrete abutments with precast concrete bridge beams forming
the deck. General infrastructure design within the site utilised
SUDS principles throughout. |
|
Heavy
Foundation Engineering, Cowie (1.2M) [ top ]

|
|
As part of continual upgrading programme at Nexfor, Cowie a new
production line was to be installed within an existing building
which had become surplus to requirements. The works comprised
the construction of extensive foundations below the existing
slab level with pits up to 4-5m deep designed to accommodate
press foundations. The works involved us in detail discussion
with the plant manufacturer in Belgium to ensure the most appropriate
solution was adopted. |
|
| Glenlyon
Road, Leven [ top ]

|
|
This project for Kingdom Housing Association
involved significant civil engineering preparatory works which
would allow the site to be developed for housing. The site was
brownfield and heavily contaminated. Other constraints included
major services which cross the site and significant topographical
features.
|
|
The solution employed on site
used significant earthworks operations to invert the soil profile
by placing contaminated material below an inert capsulation
layer. This activity allowed the site to be regraded and the
previously uncompacted fill to be placed in a controlled manner
allowing the use of raft foundations in the future development
of the site. At one end of the site a 4m high gabion basket
wall was introduced to maximise developable land. Services were
diverted to suit the proposed development layout. |
| New
Primary Feeder Road, Dundee [ top ]

|
|
This development was required as part of the overall masterplan
to construct a 200m long access road with a termination roundabout
from which individual estate roads would be constructed.
The design necessitated crossing a burn subject
to significant flood events and a box culvert solution was adopted. |


|